Following appointment by Manchester Airport Group (MAG), concrete repair and coating refurbishment works were undertaken by SUKR to return the affected parts of the structure at Manchester Airport’s Terminal 2 Carpark back to a condition factor of 1.0.
Along with this, SUKR carried out structural strengthening to six of the supporting beams to M&G (Meet and Greet) floor D. This was done in order to accommodate the additional load imposed by the Vehicle Capture Camera (VCC) unit.
Sika Ltd Carbon Fibre Reinforced Polymer (CFRP) plates were bonded to the underside of the beams in order to expedite expensive construction and minimise delays to the Terminal 2 extension programme.